(资料图)
华星东方承建的吉林省舒兰市生活垃圾焚烧发电项目烟气净化工程于2023年07月02日通过72+24小时试运行。
The flue gas purification system of the domestic waste incineration power generation project in Shulan City, Jilin Province, undertaken by our company, passed the 72+24 hour trial operation on July 2, 2023.
该项目设计规模日焚烧处理生活垃圾400吨,焚烧线采用1x400t/d机械炉排炉。烟气净化采用“炉内SNCR脱硝+半干法脱酸+干法喷射+活性炭吸附+袋式除尘器+飞灰输送、存储及稳定化工艺”的烟气净化工艺,为我司设备供货工程。
The design scale of the project is to incinerate 400 tons of domestic waste per day, where the incineration line deploys 1x400t/d mechanical grate furnace. The flue gas purification system deploys the flue gas purification process of "in-furnace SNCR denitrification + semi-dry deacidification + dry injection + activated carbon adsorption + bag filter + fly ash transportation, storage and stabilization process", this whole above system processing equipment is supplied by us for this project.
华星东方在吉林省的业绩涵盖包括:舒兰,梅河口,长春农安,德惠,长春一期、二期、三期,吉林,松原等多个项目。
Jiangsu Huaxing East’s performance in Jilin Province includes multiple projects such as Shulan, Meihekou, Changchun Nong"an, Dehui, Changchun phase I, II, and III, Jilin, Songyuan, etc.
标签: